1 Mayfair
01/06/2017 by Buildington

Works have been progressing well on site with the demolition now nearing completion to the Audley Square Car Park and the Ascott hotel, reports Cantillon.

The following activities are occurring since the last update:

• The demolition scaffold is being struck and removed from
site in line with progress
• Arisings are being removed from site for reuse/recycling.
• Existing services are being disconnected outside the site
boundary.

The following activities will be happening in June 2017:
• Continuation of demolition to 4 Audley Square, The Ascott
Hotel and Audley Square Car Park.
• Ascott Hotel demolition is complete down to ground floor
level. Sections of the building shall be demolished with the
scaffold and hoarding being progressively struck down to
footpath level. This will require temporary closures of the
footpaths to the Waverton Street and Hill Street elevations
during site working hours. Footpaths shall be reopened at
the end of each working day to allow pedestrian access to
the public.
• Further service disconnections.
• Removal of arisings from site for reuse/recycling.
• Completion of phase 1 demolition works across the site.
• Removal of arisings from site for reuse/recycling.

Source: June 2017 Newsletter from Cantillon www.audleysquareredevelopmentmayfair.com