At Blossom Street, all demolition is now complete and the groundwork activities have started.

Archaeological excavation works are near completion at Shoreditch High Street and backfilling works are taking place ahead of the future piling activities.

The 16 Norton Folgate temporary works have been installed to support the retained elements. Archaeological excavation works will start in November.

The façade retention steelwork on Commercial Street is being installed this month prior to demolition.

Read more from the community update by Cantillon for November 2019 at blossomstreet-e1.co.uk.