Keybridge

Progress Update

10/04/2020 by Buildington

The first quarter of 2020 has been packed full of productivity and progress at Keybridge, reports developer Mount Anvil. 78 homes have completed at Keybridge Tower so far.

With work on Keybridge Tower wrapping up, Keybridge Capital is on track too with the façade taking shape with metal sections, windows, insulation and vapour barrier installed up to floor 14.

The first fix of apartment party walls, underfloor heating pipework and floor screed are complete up to floor 13. Another first fix is of the plumbing and electricals, plus internal apartment partition walls are complete up to floor 10.

The plastering, bathroom tiling and timber floor laying is working its way up the floors. As is the kitchen and wardrobe installation, currently installed up to floor 5 and 4 respectively.

Last month Mount Anvil's CEO Killian Hurley joined Sara Waller (Co-Strategic Director Sustainable Growth and Opportunity, London Borough of Lambeth), and Christopher Toye (Executive Head of Wyvil Primary), at Keybridge in Vauxhall to celebrate the topping out of the building housing the new Wyvil Primary School.

The school will offer 350 more primary places for Vauxhall, along with the space and facilities to give future generations of local kids the best possible start in life.

New homes are still available for sale at Keybridge, with prices starting from £975,000 for a 2-bedroom apartment.

Contact Mount Anvil for sales.