Three Waters
Progress update December 2020

Progress update December 2020

09/12/2020 by Buildington

Three Waters by Mount Anvil is getting ready for the first completions in 2021.

The concrete frame of The City Collection has reached the 19th floor and only two floors now remain to be completed. The external precast concrete panels are fitted up to floor 4.

Internally, the party walls are complete up to floor 7, with mechanical and electrical works taking place in the corridors.

The City Collection is expected to complete in Q1/Q2 2022.

The concrete frame of The River Collection is complete. 99% of the precast concrete panels have been fitted.

The installation of the balconies has been progressing well, with all complete other than those between floors 2 and 7. The cantilevered balconies are complete to the 3rd floor.

Internally, plastering is now complete to floor 5. The individually designed kitchens have been fitted up to the second floor and they are halfway through fitting those on floor 3. Carpentry work has commenced, starting on the first floor and further progress to the flooring is commencing this week.

The River Collection is expected to complete in Q3 2021.