Hallsville Quarter
Progress update

Progress update

01/06/2021 by Buildington

Bouyigues UK reports good progress on Phase 3 of Hallsville Quarter.

Structural concrete works have reached Level 5 on Block D2 on Silvertown Way and work has started on the first floor of Block F continuing the construction of the maisonettes on Rathbone Street.

The basement level car park in Block E on Rathbone Street will be completed shortly and work has already started on the elevation of the ground floor of the building.

Phase 3 of Hallsville Quarter comprises 620 new homes including 50 extra care homes, as well as 118,404 sq ft of retail, leisure, offices and an NHS health centre.

Read more in the June 2021 issue of the Hallsville Quarter Phase 3 development newsletter available to download a hallsvillequarter.co.uk.