Construction update
19/06/2021 by Buildington
Construction update from R&F reveals that the tower structure of building No.8 is now completed and the façade installation is ongoing at Levels 47. The fit-out works are ongoing at Levels 36 to 38 and internal finishes are ongoing at Levels 32 to 33. Level 2 Marketing Suite has completed.
A temporary mock-up of a completed unit is being built at Wendle Court.