The complex demolition of the former Exhibition Centres began in December 2014 and is progressing well. Demolition to ground level of the EC2 building is now complete and demolition to ground level for the entire site is on track for completion
later this year at an expected cost of £60 million. Following this, demolition to basement level will further de-risk the site and enable the land for future development. This final phase of demolition (not currently committed) is expected to take 12 months at a cost of £30 - £40 million.

Source: Capital & Counties Properties Plc Interim Results for the six months ended 30 June 2016