21 Young Street
05/04/2017 by Buildington

Construction on site continues to progress to schedule, reports Grainger in the latest community newsletter.

The 6th floor slab is now cast and work on the 7th floor stab commencing. Internal works have also started, including the installation of the main mechanical and electrical plant in the building. The external facade work is also underway including the window installation.

Source: 19-27 Young Street Community Newsletter April 2017 19-27youngstreet.co.uk

Show all news for 21 Young Street