The Makers
02/06/2017 by Buildington

During June, McLaren will continue with the basement excavation on the Nile Street site.

Planned works for June
- Basement excavation continues
- Basement slab construction commences
- Tower crane base completed
- Site temporary power supply connected
- Tower Crane Installation

During the weekend of 8-9th July, the site will extend its opening hours to facilitate the erection of our first tower crane. A mobile crane (that will be set up in Nile Street between the junctions of Westland Place and Britannia Walk) will undertake the erection of the tower crane.

Source: McLaren's Programme Update: May 2017 nilestreetproject.com