Barts Square
15/11/2017 by Buildington

Barts Square update -

Phase One - Residential
Phase 1 of Barts Square comprises 144 residential units, 3,193 sq ft of retail and extensive public realm improvements. The residential units are being handed over to purchasers as buildings are completed with the Underwood Building (13 sales) completed by October 2017 and six further buildings (115 sales) to be completed and handed over in the period to March 2018. In total, contracts have been exchanged for the sale of 128 residential units (12 in the period) for a total value of £162.1m at an average of £1,565 psf, with a further three units reserved, leaving just 13 apartments to sell.

90 Bartholomew Close - Offices
Construction of the 24,013 sq ft office building with 6,449 sq ft of restaurant use on the ground floor is expected to be completed in December 2017. Marketing of the offices will commence after practical completion of the building. The ground floor restaurant is under offer to a leading UK restauranteur who operates a small collection of restaurants, delis and bars.

Phase Two - One Bartholomew Close - Offices
One Bartholomew Close was sold to clients of Ashby Capital LLP ("Ashby") for £102.4m in August 2015. The demolition of the existing building and the construction of a new 12-storey office block of 213,125 sq ft commenced in January 2016 and is due to be completed in Q3 2018. Ashby's clients finance the development costs and, when the building is completed and successfully let, the joint venture will be entitled to receive a profit share payment. Helical is the development manager for delivery of the project.

Phase Three - Residential/retail/offices
Demolition work on Phase 3 of Barts Square is completed with pre-construction works now underway. This phase will comprise 92 apartments and 12,197 sq ft of retail space. Completion is due in Q3 2019 and marketing of the units is expected to commence in Q2 2018. The refurbishment of 54/58 Bartholomew Close to provide 10,200 sq ft of offices is expected to start in 2018 for completion in 2019.

Via Helical Plc Half Year Results for the Six Months to 30 September 2017 investis.com.