The Silk District

Construction Update June 2020

02/06/2020 by Buildington

The Jacquard - The reinforced concrete frame has been completed and the façade and windows are now in place up to the 3d floor of the building, reports developer Mount Anvil. The internal walls are progressing well and the internal lift is being installed.

The Georgette North - The reinforced concrete frame is complete, and the façade and windows have been installed to level 2.

The Georgette South - The reinforced concrete frame is underway with the lift and stair core built up to the 9th floor.

Prices currently start from £577,500 for a studio apartment at The Georgette South.

Visit the development website for the full update.

Show all news for The Silk District