The Silk District

Progress Update

30/09/2020 by Buildington

Mount Anvil is getting closer to completion at The Georgette North.

Levels 1 to 3 are currently being decorated and will be completed in preparation for the carpets being installed in the coming two weeks.

On levels 4 to 6 the carpentry is well underway and the kitchens and bathrooms are being installed. Up at level 7, the plastering is happening at B1, while the first fix of mechanicals and electricals is taking place at B3.

The lifts have been installed and are ready for quality assurance and completion.

Externally, the brickwork is up to level 4 and the waterproofing is being taken care of on the roof.

The brickwork at The Georgette North façade has commenced. Throughout the building, each of the apartments party walls have been built and installation of the partition walls in every home has begun.

The concrete frame of The Jacuard is now built up to level 17 and the external glass façade is now at level 9. Mechanical and electrical work began last week and the partition walls are ready to be installed.

The exclusive gym, cinema and landscaping will be ready for the first resident's move-in dates in Q1 2021.