The Silk District
Construction Update

Construction Update

25/07/2022 by Buildington

Work across the 25-storey tower, The Bouchon, is running to schedule, reports Mount Anvil. In the next few weeks, the main core of The Bouchon will be complete and the pre-decoration snagging process will start from level one.

The Bouchon’s concrete frame is currently at level 23, with the building’s cladding up to level 12. Internally we’re installing the apartments’ underfloor heating, and are currently up to level nine. The carpentry teams are fitting kitchens and other woodwork up to level four.

Mount Anvil is making preparations to welcome 1400 lorry loads of concrete to the site, which is how much concrete we’ll be used to construct Phase 2’s frame.

Read more at mountanvil.com.