80 New Bond Street development progress update August 2023
During the month of July, RED Construction continued to progress well with the works to 80 New Bond Street, reports the main contractor in the August 2023 newsletter.
The team have progressed with some of the following key activities:
Dismantle of the goods hoist
Installation of the glazing to level 7
Trees and plants being positioned on the roof Garden
Progressed tiling to the showers
Progressed joinery works to all floors
Installation of permanent lighting progresses on all floors
Upcoming works within the next month will involve:
Commence joinery wall panelling in the reception
Complete all Raised access floor
Commence striking Oxford Street and New Bond Street scaffolding
Removal of the scaffold from all levels on the east lightwell
Complete landscaping to roof including planters
For more information please contact RED Construction.
For office and retail availability please the agent details on The Burlian development profile.
Photo: 80 New Bond Street newsletter on the site 22.08.2023