10 Brock Street
24/06/2011 by Buildington

Over the course of this month, construction will be underway to the east, west and central cores (via slipforms – see picture 2) to the main office building. In addition, the main market tower remains on programme to be started in early July.

The first activity in connection with the superstructure will be to install and commence the slip form construction of the central core to
the main commercial building.

Both the secondary cores to the east and west will follow shortly. In parallel with the commercial building, the slip form to both the residential market tower and the affordable block fronting Hampstead Road, will commence.

Over the course of the next 4–6 weeks, the cores will continue their rate of construction and will soon be visible above the site hoarding.

The substructure construction works continue to make good progress and the site clearance phase for both the commercial and residential are now complete.

Good progress continues to be made on the extension of the main Estate loading bay in the south-west corner of the site.

Over the course of the next month, the remaining ramp will be removed allowing works to progress to the west side of the development.

You can follow the progress of the development site on the webcams available at http://www.britishland.com

Source: Regent's Place NEQ Newsletter #13, June 20. 2011.