One Kensington Gardens
11/09/2011 by Buildington

Residents Lookahead 47 10/09/2011

De Vere Gardens Site
Week Commencing Saturday 10/09/11

Saturday:
•Slab removal and pile probing at south end of site.

Midweek:
Works Within Site-
•Phase 2 Demolition; removal of remaining buildings adjacent to Canning Passage.
•De Vere Gardens South; slab removal, pile probing and installation of piling mat.
•Façade repairs along Victoria Road Facade.
•Underpinning to number 10-14 DVG.
•Installation of Guide Wall along Victoria Road elevation
•Crushing at South end of Site

Works Around Site Boundary-
Victoria Road
•Installation of gantry stairs.

De Vere Gardens
•Installation of Stair base at north end of road.

Kensington Road
•Cabin and Gantry Steelwork Installation.

10-12 De Vere Gardens
•Underpinning to number 14 Party Wall.
•Underpinning to rear of 10-14.

Source: deveregardensdevelopment.com