St John’s Wood Square
McGee starts work on the foundation works at St John's Wood Square

McGee starts work on the foundation works at St John's Wood Square

24/05/2023 by Buildington
 
Foundation works start

McGee has been selected as the principal contractor for the next phase of the St John’s Wood Square development.


Previously responsible for asbestos removal, demolition, and preparatory works, McGee will now handle activities such as piling, excavation, concrete reinforcement, and basement bearing installations across the five-acre space. The preservation of the Grade II listed Riding School is part of this project.


For the first time, McGee will use its new Bauer BG33 piling rig, a state-of-the-art machine that's eco-friendly and ensures minimised disruption.


Timetable:

Second half of May 2023 - Start of basement construction w/c

16 May, new site entrance opens on Queen’s Terrace, preparing ground for piling

June 2023 (Anticipated date) Piling work starts


August 2023

Piling and extraction continues

First tower crane arrives on site (scheduled for 12-13 August) Temporary 2-week closure of St John’s Wood Park junction with Adelaide Road

Temporary road works on Queen’s Terrace for new power cables


September 2023

Piling and extraction continues

Concrete capping beams installation

St. John’s Wood Park junction re-opens October 2023

Piling and basement extraction continues

Concrete capping beams installation


The 2.2-hectare location, formerly the Royal Horse Artillery's base until 2012, is set between Finchley Road and Primrose Hill. It's set to become a residential area with around 120 private homes and 59 affordable rental units.


Find out more on St John's Wood Square development profile.